P3 Bid & Schedule Studio · DBFOM · 30-year concession
Value for money vs public delivery
$9.8M (3.0%)
P3 costs the public less, risk-adjusted
Capital cost
$223M
hard $166M + soft, contingency, escalation
Max availability payment, yr 1
$17.1M
$10.9M capital · $6.2M service
Private financing
6.28%
WACC on $162M financed
Substantial completion
Month 44
32-month build from close

Capital cost build-up

Hard cost line$M
Hard cost subtotal166.0
Soft costs (14%): design, permits, PM, insurance23.2
Design contingency (4%)7.6
Construction contingency (5%)8.3
Escalation to construction midpoint18.0
Capital cost (public estimate)223.1

Bid assumptions

14.0%
4.0%
5.0%
4.50%
7.0%Integrated delivery: one team designs for 30 years of upkeep, not lowest first cost.

Private partner's capital stack

Capital cost after DB savings209.8
Interest during construction14.6
Bid costs & developer fee4.2
Priced construction risk16.9
Less public milestone payment (40%)−83.9
Privately financed161.6

An illustrative model for discussion, built on the usual shape of a US availability-payment P3: a public sector comparator, risk-adjusted net present values, a milestone payment at substantial completion and a CPI-indexed availability payment with performance deductions. Every number is editable and saves in this browser. Figures are a fictional example, not a real procurement.